LINK ROADS
PROGRESS REPORT OF SPECIAL REPAIR OF LINK ROADS PHASE-7 YEAR 1998-99 PROGRESS OF LINK ROADS FOR THE YEAR 1998-1999 FOR THE MONTH ENDING 31.01.06 (MC BASSI PATHANA)
PROGRES OF LINK ROADS FOR THE YEAR 1998-1999 FOR THE MONTH ENDING 31.01.06 (MC KHAMANO)
PROGRES OF LINK ROADS FOR THE YEAR 1998-1999 FOR THE MONTH ENDING 31.01.06 (MC KHANNA)
PROGRESS REPORT OF NEW CONST. OF LINK ROADS PHASE-4 YEAR 2005-2006
PROGRESS REPORT OF NEW LINK ROADS. CONSTRUCTION DIVISION NO. 2 PWD B&R BR. MOHALI AS ON: - 31.1.06
PROGRESS REPORT UNDER RIDF-X FOR THE MONTH ENDING: 31.1.06 Links Roads
In District Fatehgarh Sahib there are 1332.86 KMs link roads, 40.37 KM length of State Highway, 19.90 KMs length for Major District roads and 128.52 KMs are Other District roads.
Out of 1332.86 KMs link roads 1011.18 KM link roads had been repaired up to 2004-05 and 81.55 KMs roads are being repaired during the year 2005-06. Similarly, out of 188.79KM State Highways, Major District roads and Other District roads 142.83 KMs had been repaired upto the year 2004-05 and 42.97KMs are being repaired during the year 2005-06. The State Highways and other major District roads have been taken up for repair/ repaired under NABARD-Vth to NABARD-Xth programme.
As per the new policy of the Punjab Govt. 18.00 KMs of roads per constituency have been taken up for new construction. The total length of these new Link roads comes to 39.66 KMs in the District i.e 18.05 KMs in Amloh, 18.12 KMs in Sirhind and 3.49 KMs in Samrala constituency. The cut off date to construct these new link roads has been fixed for 30-4-2006 .
Back to Top PROGRESS REPORT OF SPECIAL REPAIR OF LINK ROADS PHASE-7 YEAR 1998-99
Sr.No.
|
Name of Road |
Code of Road |
Target |
Estimated Cost
|
Funds Released
|
Funds Spent
|
% age of physical work done
|
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
MC Sirhind |
|
|
|
|
|
|
|
1 |
Bhangrana to Patton |
|
3.65 |
14.63 |
6.59 |
|
|
Work Started |
2 |
Sindhran to Timberpur |
|
2.42 |
8.91 |
3.99 |
|
|
Work Started |
3 |
Badali Ala Singh to Rampur |
|
4.00 |
18.30 |
16.67 |
|
|
Work Started |
4 |
Kotla Bajwara to Khera |
|
7.68 |
39.17 |
18.22 |
|
|
Work Started |
5 |
Brahmanmajra to Sadhugarh |
|
1.50 |
7.50 |
3.50 |
|
|
Work Started |
6 |
Sirhind Chuni road to Bhaironpur |
|
1.10 |
5.13 |
2.35 |
|
|
Work Started |
7 |
Pirjain to Sirhind Chunni road via Isherheil
|
|
5.44 |
29.12 |
13.52 |
|
|
Work Started |
8 |
Dangeria to Mata Shitla Devi Mandir
|
|
0.78 |
3.12 |
1.40 |
|
|
Work Started |
9 |
Jallah to Bhamarsi |
|
1.65 |
8.74 |
3.77 |
|
|
Work Started |
10 |
Saunda Head to Alipur Sodhian |
|
0.93 |
4.92 |
2.29 |
|
|
Work Started |
11 |
Madhopur to Brahmanmajra Sadhugarh road via Sadomajra
|
|
4.00 |
19.76 |
9.42 |
|
|
Work Started |
12 |
Sangatpur Sadhugarh road to Nalina Khurd
|
|
3.90 |
22.22 |
11.12 |
|
|
Work Started |
13 |
Sangatpur to Khojemajra Majri Sodhian road
|
|
1.57 |
8.29 |
3.86 |
|
|
Work Started |
14 |
Aam Khas Bagh to Sirhind City . |
|
0.92 |
4.95 |
2.29 |
|
|
Work Started |
|
Total:- |
|
39.54 |
194.76 |
98.99 |
|
|
|
Sr.No. |
Name of Road |
Code of Road |
Target |
Estimated Cost |
Funds Released |
Funds Spent |
% age of physical work done |
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
MC Chanarthal |
|
|
|
|
|
|
|
1 |
Patiala Sirhind road to Nau Lakha |
|
1.10 |
5.94 |
2.74 |
|
|
Work Started |
2 |
Halotali Sehri road to Amargarh |
|
0.85 |
3.39 |
1.50 |
|
|
Work Started |
3 |
Total |
|
1.95.. |
9.33 |
4.24 |
|
|
Work Started |
Sr.No.
|
Name of Road |
Code of Road |
Target |
Estimated Cost
|
Funds Released
|
Funds Spent
|
% age of physical work done
|
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
MC Amloh |
|
|
|
|
|
|
|
1 |
Amloh to Salan |
|
9.20 |
48.21 |
13.60 |
|
|
Work Started |
2 |
Amloh Tibbi road to Machharai Khurd
|
|
0.58 |
2.99 |
1.38 |
|
|
Work Started |
3 |
Nabha Gobindgarh road to Tibbi Khurd
|
|
9.60 |
49.98 |
23.55 |
|
|
Work Started |
4 |
Khanoura to Brainchan road up to M.C. Limit
|
|
3.50 |
18.29 |
8.60 |
|
|
Work Started |
5 |
Nabha Gobindgarh road to Badali within Link to phirni of Village Bhadhal Thuha
|
|
6.90 |
34.06 |
17.03 |
|
|
Work Started |
6 |
Bhadal Thuha Rangera road to Madararu
|
|
1.15 |
6.28 |
2.87 |
|
|
Work Started |
7 |
Bhadal Thuha Ranghera road to Bir Bhamarsi
|
|
1.48 |
7.29 |
3.65 |
|
|
Work Started |
8 |
Amloh Bhadson road to Christan Jyoti Hospital
|
|
0.30 |
1.57 |
0.71 |
|
|
Work Started |
|
Total:- |
|
32.71 |
169.30 |
71.39 |
|
|
Back to Top |
PROGRESS OF LINK ROADS FOR THE YEAR 1998-1999 FOR THE MONTH ENDING 31.1.06
NAME OF THE MARKET COMMITTEE BASSI PATHANA. (PHASE-VII)
Sr.No.
|
Name of Road |
Code of Road |
Target |
Estimated Cost
|
Funds Released
|
Funds Spent
|
% age of physical work done
|
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
1 |
Sirhind Morinda road to Wazidpur
|
|
1.20 |
5.70 |
- |
- |
- |
Stg. =0.50/0.90=55.55% Work in progress
|
|
Total |
|
1.20 |
5.70 |
- |
- |
- |
Back to Top |
PROGRES OF LINK ROADS FOR THE YEAR 1998-1999 FOR THE MONTH ENDING 31.01.06
NAME OF THE MARKET COMMITTEE KHAMANO. (PHASE-VII)
Sr.No.
|
Name of Road |
Code of Road |
Target (km)
|
Estimated Cost.
|
Funds Released
|
Funds Spent
|
% age of physical work done (PC) |
Remarks
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
1 |
L.C.ROAD TO Samadh Baba Hari Singh
|
|
0.25 |
0.57 |
- |
- |
- |
- |
2 |
Kakrala to Ucha Jataan |
|
3.12 |
12.48 |
- |
- |
- |
- |
|
Total |
|
3.37 |
13.05 |
- |
- |
- |
Back to Top
|
PROGRES OF LINK ROADS FOR THE YEAR 1998-1999 FOR THE MONTH ENDING 31.01.06
NAME OF THE MARKET COMMITTEE KHANNA. (PHASE-VII)
Sr.No.
|
Name of Road |
Code of Road |
Target (km)
|
Estimated Cost.
|
Funds Released
|
Funds Spent
|
% age of physical work done (PC)
|
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
1 |
Ajner to Muttan |
|
1.50 |
7.11 |
- |
- |
- |
Stg = 1.20/1.20 = 1003% |
2 |
Focal Point Ferozepur Damheri |
|
1.25 |
5.66 |
- |
- |
- |
Stg = 0.950/0.950 = 100% |
|
Total |
|
2.75 |
12.77 |
- |
- |
- |
Back to Top |
PROGRESS REPORT OF NEW CONST. OF LINK ROADS PHASE-4 YEAR 2005-2006
Month Ending 31. 1. 2006
Sr.No.
|
Name of Road |
Code of Road |
Target |
Estimated Cost
|
Funds Released
|
Funds Spent
|
%age of physical work done
|
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
1 |
Handali to Rajindergarh |
|
1.39 |
15.52 |
|
|
|
Work Started |
2 |
Ishereil to Bibipur |
|
1.61 |
13.96 |
|
|
|
Work Started |
3 |
Harbabspura to Majri Azim |
|
1.31 |
11.60 |
|
|
|
Work Started |
4 |
Wazirnagar to Fatehpur |
|
1.49 |
12.71 |
|
|
|
Work Started |
5 |
Jalha to Sidhwan. |
|
1.65 |
14.87 |
|
|
|
Work Started |
6 |
Balahri Khurd to Balahri Kalan |
|
1.70 |
13.68 |
|
|
|
Work Started |
7 |
Balahri Khurd to Bhaironpur |
|
1.46 |
11.79 |
|
|
|
Work Started |
8 |
Barkatpur to Rai Majra |
|
0.70 |
6.56 |
|
|
|
Work Started |
9 |
Bhaini Khurd to Patarsi Kalan |
|
1.45 |
17.72 |
|
|
|
Work Started |
10 |
Mehtabgarh to Naraina |
|
0.70 |
7.84 |
|
|
|
Work Started |
|
Total |
|
13.46 |
126.25 |
|
|
|
|
11 |
Jago Chanarthal to Bazigarh Basti
|
|
1.35 |
11.59 |
|
|
|
Work Started |
12 |
Behlolpur to Panjoli Reona Neewan
|
|
0.80 |
13.27 |
|
|
|
Work Started |
13 |
Balpur to Chanarthal Mandi |
|
3.25 |
33.45 |
|
|
|
Work Started |
|
Total |
|
5.40 |
58.31 |
|
|
|
|
14 |
Rangheri Harizen Basti to Jhambala
|
|
0.844 |
8.20 |
|
|
|
Work Started |
15 |
Mararu to Bhari Panecha |
|
1.099 |
10.79 |
|
|
|
Work Started |
16 |
Habitpur to School |
|
0.50 |
4.58 |
|
|
|
Work Started |
17 |
Bazigarh Basti to Khumb to Grid road
|
|
0.13 |
1.83 |
|
|
|
Work Started |
18 |
Brounga to Aniyan road. |
|
2.107 |
19.18 |
|
|
|
Work Started |
19 |
Nabha Gobindgarh road to Bridge to Dera Baba Biram Dass.
|
|
0.30 |
2.85 |
|
|
|
Work Started |
20 |
Bhadal Thuha Ghulo majra to Gurd. Sahib
|
|
0.15 |
2.72 |
|
|
|
Work Started |
21 |
Bazigarh to D euan via house of Mukhtair Singh
|
|
0.50 |
4.73 |
|
|
|
Work Started |
22 |
Rurkee to Harizen Basti |
|
0.40 |
3.78 |
|
|
|
Work Started |
23 |
Paheri to Harizen Basti |
|
0.35 |
3.39 |
|
|
|
Work Started |
24 |
Salana Dara Singh to Manji Sahib Gurd.
|
|
0.55 |
5.12 |
|
|
|
Work Started |
25 |
Salana to Marrian. |
|
0.30 |
2.92 |
|
|
|
Work Started |
26 |
Bhanbri to Bugga road. |
|
0.65 |
5.94 |
|
|
|
Work Started |
27 |
Badali to Fatehpur Mullanpur. |
|
1.00 |
10.32 |
|
|
|
Work Started |
28 |
Bhagwanpura to Bhari. |
|
0.47 |
5.78 |
|
|
|
Work Started |
|
Total:- |
|
9.350 |
92.13 |
|
|
|
Back to Top |
PROGRESS REPORT OF NEW LINK ROADS. CONSTRUCTION DIVISION NO. 2 PWD B&R BR. MOHALI AS ON: - 31.1.06
MC: - KHAMANO CONSTITUENCY SAMRALA
Sr.No.
|
Name of Road |
Code of Road |
Target (km)
|
Estimated Cost. (in lacs)
|
Funds released |
Funds Spent
|
% physical work done (PC)
|
Remarks
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
1 |
Khanna Khammano road to sarav hitkari Vidya Mandir Khammano |
|
2.33 |
20.04 |
- |
- |
- |
E/W =2.33/2.33=100% work in progress
|
2 |
Qttala Bhari to Khanna road via Barwali khurd |
|
1.66 |
10.77 |
- |
- |
- |
E/W = 1.16/1.16 = 100% soling=0.50/1.16=43.10% work in progress
|
|
Total |
|
3.49 |
30.81 |
- |
- |
- |
Back to Top |
PROGRESS REPORT UNDER RIDF-X FOR THE MONTH ENDING: 31.1.06
Sr.No.
|
Name of Road |
Code of Road |
Target (km)
|
Estimated Cost. (in lacs)
|
Funds released |
Funds Spent
|
% physical work done (PC)
|
Remarks
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
1 |
Rsg./Wdg./Stg. Bassi Bagh Sikander via Jarkhelan Kheri Road
|
|
9.35 |
177.91 |
47.99(T.O)+
62.49 (C.E)
|
- |
- |
Tender submitted ti Circle office for approval
|
2 |
Rsg./Stg. Sirhind Morinda to Bassi Sanghol Road |
|
5.12 |
101.23 |
- |
- |
Work in progress Raising = 0.60 upto GSB completed Stg:- 4.00(88.49%) Upto Ist coat: 3.50 Km 10 span slab type culvert complete.
|
3 |
Re-constn./Stg. Of Nogawan Karimpura Kotla Road |
|
6.50 |
67.96 |
- |
- |
Work in progress Raising = 0.60 upto GSB completed Stg:- 4.40 Km (73.33%) Upto Ist coat: 4.00Km
|
|
Total |
|
20.97 |
347.41 |
110.48 |
- |
- |
Back to Top |
|